Construction Quality Control: Complete Guide
Construction quality control is the set of inspections, tests and records that confirm the works have been built in line with the design, the specification and the contract. This guide explains how quality control works on site, from the inspection and test plan and hold points to non-conformance reports and handover records, and how to keep the evidence organised with Atsep Inspection. The principles apply to residential, commercial and infrastructure projects in any country.Key Takeaways
- Construction quality control verifies that completed work meets the specified requirements, while quality assurance builds the system of plans, procedures and responsibilities that makes this verification repeatable.
- An inspection and test plan (ITP) lists each activity together with its reference document, acceptance criterion, type of verification (hold, witness or review) and the record to be produced.
- A hold point is a stage defined in the ITP or other project quality documentation at which work must not proceed until the required inspection or approval is completed and the point is formally released; it is a key control for concealed works where the project defines it.
- ISO 9001:2015 requires nonconforming outputs to be identified and controlled under clause 8.7 and addresses corrective action in clause 10.2; site non-conformance report (NCR) procedures commonly apply similar principles by documenting the non-conforming work, its disposition and the subsequent verification.
- FIDIC 2017 contracts deal with quality in Clause 7 (samples, inspection, testing and rejection), and Sub-Clause 4.9 addresses quality management; the exact obligations always come from the particular contract.
- A useful NCR records at least the location, requirement not met, evidence, responsible party, corrective action or disposition, target date and the result of re-inspection; significant or recurring non-conformances also call for a documented root-cause analysis.
- Records made on the day of the inspection – with date, time, description and photos – are the evidence of quality control, and Atsep Inspection generates DOCX or PDF reports directly from them.
What Is Construction Quality Control?
Construction quality control (QC) is the process of checking, on site and against defined criteria, whether the work that has been carried out meets the requirements of the design, the specification, the applicable standards and the contract. It answers a simple question for every element of the works: does what has been built match what was required, and can this be demonstrated?
Quality control is often confused with two related terms, although quality assurance and quality control are commonly discussed together as construction QA/QC. Quality assurance (QA) concerns the management system: the planning, procedures, competence and responsibilities that are meant to prevent problems. Inspection and testing are the individual activities that produce the evidence. The table below shows how they fit together.
| Term | Main question | Typical activities | Typical output |
|---|---|---|---|
| Quality assurance | Is the system in place to achieve the required quality? | Quality plan, procedures, competence and responsibilities, supplier approval | Quality plan, procedures, audit records |
| Quality control | Does the completed work meet the requirements? | Inspections, tests, measurements, release of work, handling of non-conformances | Inspection records, test results, NCRs |
| Inspection and testing | What is the actual condition of this element? | Visual checks, dimensional checks, sampling, laboratory and on-site tests | Checklists, protocols, photos, test reports |
Requirements differ between countries, projects and contracts. Building regulations, the employer’s requirements, the specification and the standards referenced in the contract define what must be checked and how. This guide describes general principles, and the documents of your own project always take precedence.
Building a Quality Control Framework: Plans, ITPs and Responsibilities
Quality control works best when it is planned before the work starts. Checking quality only at the end leaves no chance to correct concealed elements, which is why the plan has to define what will be inspected, at which point and by whom.
Quality plan and method statements
A project quality plan describes how the contractor will manage quality on a particular project. ISO 10005:2018 provides guidelines for establishing, reviewing, accepting, applying and revising quality plans. It is guidance and not a set of requirements, so the contract decides whether a quality plan is needed and what it must contain.
On many projects, method statements complement the plan. A method statement describes how a particular activity will be carried out, including the sequence of work, resources, controls and precautions. The inspection and test plan then defines when and how the completed stages are inspected or tested against the specified acceptance criteria.
Inspection and test plan (ITP)
The inspection and test plan is the practical tool of quality control: a table that lists the activities to be verified and the way each one is checked. A typical ITP defines the following:
| ITP column | What it defines |
|---|---|
| Activity or element | The work to be checked, for example a stage of a structural element or an installation |
| Reference document | Drawing, specification clause, standard or manufacturer instruction that sets the requirement |
| Inspection or test | What is checked or measured and by which method |
| Acceptance criterion | The value, tolerance or condition that must be met, taken from the project documents |
| Verification type | Hold point, witness point or review of documents |
| Record | The document or evidence produced: checklist, protocol, test report, photos |
The acceptance criteria should never be invented or copied from another project. They come from the design, the specification and the standards that apply to the works, and where a requirement is unclear it should be clarified with the designer before the work proceeds.
Hold points, witness points and review
A hold point is a stage defined in the ITP or other project quality documentation at which work must not proceed until the required inspection or approval has been completed and the point has been formally released. A witness point gives the inspector the right to be present, but the work may proceed if the inspector does not attend after proper notice. A review point covers documents such as certificates, delivery notes or test results. The contract or the quality plan should state who may release each point and how much notice is required.
Inspection requests (IR and WIR)
On many projects, the contractor submits an Inspection Request (IR) or Work Inspection Request (WIR) when a stage is ready for inspection. The request links the work to be inspected with the relevant drawing, the ITP activity and the acceptance criteria, while the inspection record documents whether the work was accepted, rejected or accepted with comments. The terminology and the approval workflow differ between projects and contracts, so the procedure agreed in the project documents should be followed.
On many international projects these documents form a chain: quality plan, method statement, ITP, inspection request and, where a problem is found, a non-conformance report.
Roles and responsibilities
Contractor
Carries out the works, performs its own checks, notifies the inspector before hold points, keeps the records and corrects non-conforming work.
Inspector, engineer or supervisor
Verifies the work on behalf of the employer or investor, witnesses tests, releases hold points and records findings.
Other participants, such as the designer, the independent testing laboratory or a third-party certifier, may also have defined roles. Their responsibilities should be written down in the contract documents, so that nobody has to guess who is allowed to approve what.
Quality Control Stages on a Construction Site
Quality control follows the sequence of the works. A practical way to organise it is to divide the project into stages and to define for each of them the checks that cannot be postponed. The following table presents typical activities; the list for a real project must come from its ITP and its documents.
| Stage | Typical quality control activities | Typical records |
|---|---|---|
| Before works start | Review of drawings and specification, approval of materials and subcontractors, setting out check | Approved material submittals, setting-out record |
| Delivery of materials | Check of delivery documents, product labelling and visible condition, storage conditions | Delivery notes, certificates, traceability records, photos of deliveries |
| During execution | Checks of dimensions, levels, workmanship and conformity with the drawings, tests defined in the ITP | Inspection checklists, test reports, daily entries |
| Before covering | Inspection of concealed elements before the next layer or trade is installed; release of hold points where the ITP defines them | Release of hold point, photos with scale, protocols |
| Completion | Functional tests, final inspection, list of outstanding items, verification of corrections | Test certificates, snagging list, as-built information |
Materials and delivered products
Quality control begins when materials arrive on site. Delivery documents, labelling and visible condition are compared with the approved submittal and the specification, and storage conditions are checked so that products are not damaged before installation. Where a standard or the specification requires sampling or testing of a material, the sampling method and the laboratory should be defined in advance. For concrete, for example, European practice refers to standards such as EN 206 for concrete and the EN 12390 series for testing hardened concrete, where those standards apply to the project.
Material traceability
Material traceability is another important part of quality control. Where required by the specification, records should make it possible to link installed materials or products to their delivery documentation, certificates, batch or heat numbers, test results and their final location in the works. This is particularly important for structural steel, concrete, reinforcement and safety-critical products.
Concealed works
Concealed works deserve the strictest control, because an error found after covering means opening up the structure. Reinforcement, formwork, embedded services, waterproofing, insulation and pipework should be inspected before they are concealed. Where the ITP defines a hold point, the work should not proceed until that point has been formally released. Where relevant, the execution standard referenced by the project defines additional requirements; examples are EN 13670 for the execution of concrete structures and EN 1090-2 for steel structures, whose execution classes affect the scope of inspection.
Testing and commissioning
Functional tests of installations, pressure and leak tests, load tests and similar procedures are carried out according to the specification and the relevant standards. The result of each test should be recorded together with the date, the method, the person responsible and the conclusion. A failed test leads to correction and a repeated test, and the repeat should also be recorded.
Completion, snagging and handover
Before handover, the works are inspected as a whole, outstanding items are listed and each correction is verified. This last stage collects the records from the entire project and forms the basis of the handover file. A complete set of records from earlier stages makes this inspection faster, because the history of every concealed element is already documented.
Handling Non-Conformances and Corrective Action
A non-conformance is work, material or documentation that does not meet the specified requirement. The aim of quality control is not only to find such cases but to manage them in a consistent way. ISO 9001:2015 requires nonconforming outputs to be identified and controlled under clause 8.7 and addresses corrective action in clause 10.2. Site NCR procedures commonly apply similar principles by documenting the non-conforming work, its disposition and the subsequent verification.
A typical non-conformance process on site has the following steps:
- Identify the problem and describe it factually: location, element and the requirement that is not met.
- Record the evidence with photos, measurements and the reference to the drawing or specification clause.
- Notify the responsible party and, where required by the contract, the engineer or the designer.
- Agree the disposition and the correction: repair, replacement, additional testing or a design decision. A deviation from the design should be approved by the person authorised to do so.
- Set a deadline and assign responsibility for the correction.
- Re-inspect the corrected work and close the NCR with a record of the result.
A correction deals with the particular defective work, whereas corrective action addresses the cause of the non-conformance so that it does not recur. For significant or recurring non-conformances, root-cause analysis and preventive or corrective measures should also be documented.
Under FIDIC 2017 contracts, the engineer may reject work, plant or materials that do not comply with the contract, and the contractor is obliged to remedy the defect; the detailed procedure and time limits are set out in the particular contract and should be followed exactly. It is also worth remembering that a repair is not only a technical matter. Corrections affect the programme and cost, so each NCR should have a date, an owner and a closing record.
Documenting Quality Control: Records, Photos and Reports
Quality control that is not recorded cannot be demonstrated. Records are what the investor, the engineer, the insurer or an arbitrator will ask for when a question arises months or years later. For this reason each inspection should leave a trace that answers five questions: what was checked, where, when, by whom and with what result.
Good records share several features:
- They are made at the time of the inspection and not reconstructed afterwards.
- They contain a date, a time and a precise location of the element.
- They link photos to a specific description, so that an image cannot be separated from its meaning.
- They refer to the requirement, and to the current approved revision of the drawing or specification, against which the work was checked.
- They state the result and any action that has been agreed.
- They can be found quickly and exported in a form suitable for the client or the engineer.
For concealed works, a useful method is to take a general view showing the location, a detail of the element and, where a dimension matters, a detail with a tape measure or scale in view. A short description should state what was done and at which stage. Detailed guidance is provided in the article on the construction site diary app. It is also important to remember that a private record does not replace any statutory register or formal notice required by the law of the country or by the contract.
How Atsep Inspection Supports Construction Quality Control
Atsep Inspection is an application for recording inspections on site. Its variants support two different parts of quality control, and the choice depends on the task: a chronological record of what happened on site, or management of defects through to rectification.
Jurnal – chronological site record
Entries with date, time, description and photos, displayed from the earliest to the latest and exported as DOCX or PDF reports. Suitable for recording inspections, concealed works and agreements. See the Jurnal construction site diary.
Engineer – defect management
Defects are created, marked on drawings, assigned to contractors, given severity levels and monitored through the whole rectification process. See construction inspections with Atsep Inspection.
In practice, the Jurnal variant helps to keep the evidence of inspections and hold points in one place, because each entry has an exact date and time, and photos remain attached to the entry. The Engineer variant supports the non-conformance process: a defect has a location on the drawing, a responsible contractor and a status that can be followed until it is corrected. You can read how the application works in the how to use guide.
The application organises and presents your records; it does not define acceptance criteria or replace the judgement of the person carrying out the inspection. The requirements, tolerances and test methods still come from the project documents and standards.
Common Construction Quality Control Mistakes
- No plan before the work starts. Without an ITP, hold points are identified too late or not at all.
- Inspection after covering. A concealed element that was not inspected before covering can be verified only by opening up the structure.
- Working from outdated drawings. Inspections should verify the work against the current approved revision of the drawing, specification or method statement. Using superseded documents can result in compliant workmanship being applied to the wrong requirement.
- Vague acceptance criteria. Statements such as “correct workmanship” cannot be verified; each criterion should refer to a drawing, a specification clause or a standard.
- Photos without context. An image with no date, location or description rarely proves anything later.
- NCRs without owners and deadlines. A non-conformance that nobody is responsible for tends to remain open until handover.
- No re-inspection. A correction is not complete until it has been checked and the result recorded.
- Records written long after the event. Notes reconstructed from memory are less reliable than entries made at the time of the inspection.
Summary
Construction quality control is a planned process, not a final check. It starts with a quality plan and an inspection and test plan, continues through inspections, tests and hold points for each stage of the works, and ends with verified corrections and a complete set of records at handover. Concealed works need the most attention, because they cannot be checked later without opening up the structure.
Every non-conformance should be recorded with its evidence, an owner, a deadline and a re-inspection result, and every inspection should leave a dated record with photos. Atsep Inspection helps to keep such records organised: Jurnal for the chronological history of the site, and the Engineer variant for defects and their rectification. Requirements and acceptance criteria always remain those of your project, your contract and the standards that apply to it.
Keep your quality control records in one place
Record inspections with date, time, description and photos, then generate a DOCX or PDF report whenever you need it. Learn more about Jurnal and construction inspections in Atsep Inspection.
Frequently Asked Questions (FAQ)
What is construction quality control?
Construction quality control is the process of inspecting and testing the work on site to confirm that it meets the requirements of the design, the specification, the applicable standards and the contract. It includes planned inspections, tests, release of work at hold points, handling of non-conformances and keeping records that prove the results.
What is the difference between quality assurance and quality control in construction?
Quality assurance concerns the management system: the quality plan, procedures, responsibilities and competence intended to prevent defects. Quality control concerns the verification of the work itself through inspections and tests. Assurance sets up the framework, and control produces the evidence that the work meets the requirements.
What is an inspection and test plan (ITP) in construction?
An inspection and test plan is a document that lists the activities to be verified on a project, the reference document for each requirement, the acceptance criterion, the type of verification (hold point, witness point or review) and the record to be produced. It is prepared before the work starts and is agreed with the party that supervises the works.
What is a hold point in construction quality control?
A hold point is a stage defined in the ITP or other project quality documentation at which work must not proceed until the required inspection or approval has been completed and the point has been formally released. On many projects hold points are set before concealed works are covered, for example reinforcement before concreting, but only where the project documents define them.
What should a non-conformance report include?
A non-conformance report should state the location and element, the requirement that has not been met, the evidence such as photos and measurements, the responsible party, the agreed corrective action or disposition and the target date. It should also record the result of the re-inspection, so that the report can be formally closed.
How can a construction inspection app help with quality control?
An inspection app keeps records made on site in one place: each entry has a date and time, a description and photos, and reports can be exported without retyping. With Atsep Inspection, the Jurnal variant provides a chronological site record, while the Engineer variant manages defects with drawings, assigned contractors, severity levels and rectification tracking.