Quality Assurance vs Quality Control in Construction

Quality assurance vs quality control in construction comes down to a simple distinction: QA builds confidence that the quality system will deliver the required result, while QC inspects and tests what has actually been built. This guide explains both terms using the ISO 9000:2015 definitions, compares them side by side, shows how they work together on a project and describes how to keep the records that prove both with Atsep Inspection.

Key Takeaways

  • ISO 9000:2015 describes quality assurance as the part of quality management focused on giving confidence that quality requirements will be fulfilled, and quality control as the part focused on fulfilling them; in practice QA concerns the system and QC concerns the work.
  • Construction QA typically covers the quality plan (ISO 10005:2018 gives guidance), procedures, competence, control of suppliers and subcontractors, and audits, while QC covers inspections, tests, hold points and non-conformance reports (NCRs).
  • ISO 9001:2015 does not divide its requirements into QA and QC clauses; related provisions include 8.4 (external providers), 8.6 (release of products and services), 8.7 (nonconforming outputs), 9.2 (internal audit) and 10.2 (corrective action).
  • QC produces evidence about the work, and QA uses that evidence, together with internal audits (clause 9.2) and management review (clause 9.3), to judge whether the quality system is effective.
  • Responsibilities for QA and QC differ between contracts and countries; the contractor, subcontractors, the employer’s engineer, the designer and testing laboratories should have their roles written down in the project documents.
  • The inspection and test plan (ITP) is a QC tool, but it is defined within the QA framework, together with the quality plan and method statements.
  • Both functions rely on dated records, and Atsep Inspection supports them with entries that carry date, time, description and photos, exported as DOCX or PDF reports.

Quality Assurance and Quality Control in Construction: Definitions

The terms quality assurance and quality control are used so often together as “construction QA/QC” that their meanings tend to merge. The international vocabulary standard ISO 9000:2015 separates them precisely. Quality assurance is the part of quality management that aims to give confidence that the quality requirements will be fulfilled. Quality control is the part that is concerned with fulfilling those requirements through operational activities.

Translated into construction language, QA answers the question: have we organised the project so that the required quality can reliably be achieved, and can we show it? QC answers a different question: does this particular piece of work meet the requirements of the design, the specification and the contract? The first question is about planning, procedures, people and oversight, and the second is about verification of the actual work.

An often repeated statement says that QA prevents defects and QC detects them. It is a useful shortcut, but the ISO wording is more precise. QA is about confidence in the system, and QC is about fulfilling the requirements, which also includes measures that prevent defects during execution. The boundary between the two is therefore not always sharp, and many organisations manage them through one joint QA/QC team.

Key Differences Between QA and QC in Construction

The table below summarises the typical differences. It describes common practice, and the details depend on the contract and on the quality management system of the organisation.

Aspect Quality assurance (QA) Quality control (QC)
Main question Is the system capable of delivering the required quality, and can this be shown? Does the completed work meet the requirements?
Orientation Processes, procedures, people and management system Materials, workmanship and finished elements
Typical activities Quality plan, procedures, competence, supplier approval, internal audits, management review Inspections, tests, measurements, hold points, release of work, NCRs
Typical documents Quality plan, method statements, ITP (as a plan), procedures, audit reports, training and calibration records Completed ITP records, inspection requests, checklists, test reports, photos, NCRs
Typically performed by Quality manager, QA engineer, management QC inspector, site engineer, supervisor, testing laboratory
Result Confidence in the quality system Evidence about the condition of the work

The most important conclusion from the table is that the two functions do not compete. A strong QC process inside a weak QA system produces records without learning from them, and a well-designed QA system without QC has no evidence that it works.

Quality Assurance in Construction: What It Covers

Quality assurance on a construction project is built before the first inspection takes place. Its purpose is to make sure that the requirements are understood, that the people and methods are suitable and that there is a mechanism to check whether the system works. The following elements form its core.

Quality plan and procedures

A project quality plan describes how quality will be managed on a particular project. ISO 10005:2018 provides guidelines for establishing, reviewing, accepting, applying and revising quality plans; it is guidance and not a set of requirements, so the contract decides whether a plan is needed and what it must contain. On many projects, method statements describe how particular activities will be carried out, including the sequence of work, resources, controls and precautions.

Competence, suppliers and subcontractors

ISO 9001:2015 requires organisations to determine and ensure the competence of persons doing work that affects quality (clause 7.2) and to control externally provided processes, products and services (clause 8.4). In construction, this translates into the approval of subcontractors and suppliers, the verification of qualifications where the contract requires them, and the definition of requirements passed down the supply chain.

Document control and measuring equipment

Quality assurance also ensures that the right documents reach the people who need them. Controlled documents, including drawings, specifications and procedures, should be available in their current approved revision. Measuring and testing equipment used for acceptance decisions should be suitable for its purpose and, where required, calibrated or verified (ISO 9001:2015, clause 7.1.5).

Audits, review and improvement

Internal audits (clause 9.2) check whether the system is implemented and effective, and management review (clause 9.3) evaluates its performance. When nonconformities are found, corrective action (clause 10.2) addresses their causes so that they do not recur. This feedback loop is what differentiates quality assurance from a collection of inspections: it uses the results of control to improve the way the work is organised.

Quality Control in Construction: What It Covers

Quality control takes place on site and in the supply chain, and it verifies the work against defined criteria. The criteria come from the design, the specification, the applicable standards and the contract, and they should never be invented or taken from another project. The main QC tools are described below.

Inspection and test plan, hold points and inspection requests

The inspection and test plan (ITP) lists the activities to be verified, the reference document, the acceptance criterion, the type of verification and the record to be produced. A hold point is a stage defined in the ITP or other project quality documentation at which work must not proceed until the required inspection or approval has been completed and the point has been formally released. On many projects, the contractor submits an Inspection Request (IR) or Work Inspection Request (WIR) when a stage is ready for inspection. The terminology and workflow differ between projects, so the procedure agreed in the project documents applies.

Inspections and tests

Inspections check materials on delivery, workmanship during execution and concealed elements before they are covered. Tests are carried out according to the specification and the relevant standards; for concrete, for example, European practice refers to EN 206 and the EN 12390 series where those standards apply to the project. Results are compared with the acceptance criteria, and the work is released, rejected or accepted with comments according to the project procedure.

Non-conformances and re-inspection

When work does not meet the requirement, it is recorded as a non-conformance. ISO 9001:2015 requires nonconforming outputs to be identified and controlled under clause 8.7, and it addresses the release of products and services in clause 8.6. A useful NCR records at least the location, the requirement not met, the evidence, the responsible party, the corrective action or disposition, the target date and the result of re-inspection. For significant or recurring non-conformances, a root-cause analysis may also be required to determine why the problem occurred and what action is needed to prevent recurrence; this is where QC passes information back to QA.

How QA and QC Work Together on a Project

On a well-managed project, QA and QC form a single cycle. The quality system defines what must be done and checked, the control activities verify the work, and the results are used to correct both the work and the system. On many international projects the documents follow a chain: quality plan, method statement, ITP, inspection request and, where a problem is found, a non-conformance report.

  1. QA defines the requirements, the quality plan, the responsibilities and the procedures.
  2. Method statements describe how each activity will be carried out, and the ITP defines when and how the work will be inspected or tested.
  3. QC carries out inspections and tests, releases hold points and records the results.
  4. Non-conformances are recorded, corrected and re-inspected.
  5. QA reviews the results, for example the number, type and causes of NCRs, through audits and management review.
  6. Corrective actions and actions addressing risks and opportunities may lead to changes in procedures, training, controls or supplier arrangements, and the cycle starts again.

Who is responsible for QA and QC?

There is no universal allocation of responsibilities, because it follows from the contract, the procurement method and the national regulations. The table presents the usual division, which should always be confirmed in the project documents.

Role Typical QA responsibilities Typical QC responsibilities
Contractor Quality plan, procedures, competence, supplier control, internal audits Own inspections and tests, notification of hold points, correction of non-conformances
Subcontractors and suppliers Compliance with the quality requirements passed down by the contractor Inspection and records of their own work and products
Employer, engineer or supervisor Review and acceptance of the quality plan, audits where the contract allows them Inspection, witnessing of tests and release or acceptance of work where required by the contract
Designer Clear and consistent design documents under revision control Clarifications and approval of deviations from the design
Testing laboratory or third party Own quality system and competence Sampling and testing according to the specification

On larger construction projects, these responsibilities are often coordinated by QA/QC managers and QA/QC engineers, while individual inspections may be performed by QC inspectors, site engineers, supervisors or specialist testing personnel.

A contractor that holds an ISO 9001 certificate has a certified quality management system, but the certificate does not by itself demonstrate that a particular element of a particular building was built correctly. That evidence comes from QC records for the project.

Example: QA and QC for Reinforced Concrete

The difference between the two functions is easiest to see on a single element. The description below shows a typical sequence for reinforced concrete; the actual stages, criteria and tests always come from the project documents and the standards that apply.

QA – preparing the control system

The contractor establishes the concrete procedure, approves the concrete supplier, verifies the competence of personnel, prepares the method statement and the ITP, defines inspection stages and ensures that current approved drawings are available to the people who need them.

QC – controlling the element

Before concreting, the reinforcement, formwork, dimensions, embedded items and concrete cover are inspected against the approved drawings and acceptance criteria. Concrete delivery documentation is checked, samples are taken where required and test results are recorded.

If a requirement is not met, the work is recorded as non-conforming and handled according to the NCR procedure of the project. Where the ITP defines a hold point before concreting, the work does not proceed until that point has been formally released. In short, QA prepares the system of control, and QC carries out the specific control of the element.

Records for QA and QC: How Atsep Inspection Helps

Both functions depend on evidence. QC generates inspection records, test reports, photos and NCRs, while QA draws on those records, together with audit reports, training and calibration records, to judge the system. If records are made late, are incomplete or cannot be found, neither function can show what it has done.

Atsep Inspection supports mainly the control side by keeping the records of site work organised. Jurnal is the variant for a chronological site record: each entry has a date and time, a description and photos, and entries can be exported as DOCX or PDF reports. See the Jurnal construction site diary. The Engineer variant is designed for defect management, where defects are marked on drawings, assigned to contractors, given severity levels and monitored through rectification. See construction inspections with Atsep Inspection. The how to use guide explains the workflow in detail.

What the application does

It keeps dated entries, photos and defect records in one project, and generates reports from them, so the history of inspections and corrections can be reviewed.

What it does not do

It does not define acceptance criteria, replace the quality management system or take the place of the judgement of the person carrying out the inspection.

It is also worth remembering that a private record does not replace any statutory register or formal notice required by the law of the country or by the contract.

Common Misconceptions About QA and QC in Construction

  • QA is paperwork and QC is the real work. The quality system determines whether inspections are planned at the right points, by competent people, against correct criteria. Without it, QC is improvised.
  • QC alone is enough. Inspections without audits, review and corrective action find defects but do not remove their causes.
  • QA guarantees that no defects will occur. The ISO definition speaks of confidence that requirements will be fulfilled, which is not the same as a guarantee.
  • An ISO 9001 certificate proves the quality of every project. It relates to the management system of the organisation, and project-specific evidence still has to be produced.
  • A software tool replaces the quality system. An application organises records, but the plan, the procedures and the acceptance criteria must still be defined by people.
  • QA and QC must always be separate departments. The functions are different, but the organisation can be structured in different ways, provided that responsibilities are clear and documented.

Summary

Quality assurance and quality control in construction are two parts of one quality management approach. QA gives confidence that the system is capable of delivering the required quality, through planning, procedures, competence, supplier control, audits and corrective action. QC verifies the actual work through inspections, tests, hold points and non-conformance reports.

The two work as a cycle in which QC provides evidence and QA uses it to improve the way the project is run. Responsibilities, acceptance criteria and procedures always come from the project documents, the contract and the standards that apply. Atsep Inspection helps to keep the records of this cycle organised: Jurnal for the chronological history of the site, and the Engineer variant for defects and their rectification.

Keep your QA and QC records in one place

Record inspections with date, time, description and photos, track defects through rectification and generate a DOCX or PDF report whenever you need it. Learn more about Jurnal and construction inspections in Atsep Inspection.

Frequently Asked Questions (FAQ)

What is the difference between quality assurance and quality control in construction?

Quality assurance concerns the quality management system: planning, procedures, competence, supplier control and audits that give confidence the requirements will be met. Quality control concerns the verification of the actual work through inspections and tests against the design, specification and contract. QA looks at the system, and QC looks at the result.

Is quality control part of quality assurance?

ISO 9000:2015 describes both quality assurance and quality control as parts of quality management, each with a different focus. In practice the two are closely linked, because QC activities produce the evidence on which QA relies to assess whether the quality system works. Many organisations manage them together as QA/QC.

Who is responsible for quality assurance and quality control on a construction site?

The allocation depends on the contract and on national regulations. Usually the contractor is responsible for its quality plan and for its own inspections and tests, while the employer, the engineer or a third party verifies the work and, where the contract requires it, releases hold points or accepts the work. Subcontractors, the designer and testing laboratories have defined roles that should be written in the project documents.

Which ISO 9001 clauses relate to quality assurance and quality control in construction?

ISO 9001:2015 does not split its requirements into QA and QC clauses. Provisions commonly related to them include clause 7.2 (competence), 8.4 (externally provided processes, products and services), 8.6 (release of products and services), 8.7 (nonconforming outputs), 9.2 (internal audit), 9.3 (management review) and 10.2 (nonconformity and corrective action).

What are examples of QA and QC activities in construction?

Typical QA activities are preparing the quality plan and procedures, approving suppliers and subcontractors, ensuring competence and document control, carrying out internal audits and managing corrective action. Typical QC activities are inspecting materials and work, performing tests, releasing hold points, recording non-conformances and verifying corrections.

Can an inspection app support both quality assurance and quality control?

An inspection app mainly supports quality control by keeping dated entries, photos and defect records organised, and the same records can be reviewed as part of quality assurance. With Atsep Inspection, Jurnal provides a chronological site record and the Engineer variant manages defects, but the app does not replace the quality management system or define acceptance criteria.